Comment Learn from OUR Mistakes... (Score 1) 422
Run Multiple cirruct for basic Power
Manufacturing - Conditioned power for high power electronics - basic power for lights, blowers, vacuum cleaner and utility used.
Offices - Central hard wired UPS to all desk for PC only. Conditioned line for printers and other electronics. Utility power (can be conditioned or not) for lights, cleaning and such.
Network CAT 6 wire within Building: Can be run beside or together with Telephone wire (if not going for IP phones) use SAME Cat 6 wire - different colors (we used BLUE for Data/network and GREY for Telephone - Network A and Network B) . Make sure you run copper and fiber to to building (even if fiber is not yet available).
Use Wiring Trays for any wire over 10 to all area in building (easy to ADD more cables at a later time that way). EMT Conduit or other wiring channels for any runs with 10 or less. Single drops (telephone and data wire - within walls) don't need conduit - but suggested. All Surface mount in Manufacturing area should be conduited or use SHELDED wire. All should be terminated on all ends with a female jack attached to a hard surface.
Router/Switch should be POE Plus - Power Over Ethernet Plus standard - so you can install Wireless points of access without running power. Or for IP video security Cameras etc....
Install about 25% more runs that you think you need. Switch/Router/termination points - should be over-sized by 50% to 100%
Just my 2 cents.....